Hong Kong’s rail operator will use skidding, a world first for heavy rail, to build Hung Shui Kiu Station beside an active line and keep it on track for completion in 2030.
MTR Corporation said that crews are assembling two 10,000-tonne station structures from prefabricated parts about 30 meters from either side of the elevated Tuen Ma Line.
"This innovative construction method significantly reduces the need for works during non-traffic hours, greatly reduces construction risks and secures project progress," the South China Morning Post quoted Carl Devlin, the corporation’s capital works director, as saying.
Conventional construction would leave crews with just two hours each night for much of the work, when trains stop running. Alan Yan Wai-ming, MTR’s head of project delivery, told The Standard that the short window would pose safety risks and could add years to the project.
Each structure is about 210 meters long, 15 meters wide and 20 meters high, and weighs about as much as 100 blue whales. Hydraulic jacks will lift the structures slightly so they can slide along fixed guide tracks into place.
Yan compared the move to a group of people carrying a heavy object together. The jacks must move in sync to keep each structure stable and position it with millimeter precision.
Foundation work is nearly complete, and about a quarter of one platform structure has taken shape.
Hung Shui Kiu Station will sit between Tin Shui Wai and Siu Hong stations. It will eventually connect to the planned Hong Kong-Shenzhen Western Rail Link and a local mass transit system, forming a major cross-border transport hub for the Northern Metropolis development.